Working calendar:
Below is a basic schedule that I will be following in order to finish all work in a timely fashion.

Marking Period 1 Schedule/Calendar

Due dates:
Calendar- 9/13/13  
Background information- 9/16/13
Design brief- 9/16/13
Specifications and limitations- 9/16/13
Summer research/brainstorming- 9/16/13
Informal presentation- 9/18/13
Rationale report- 9/23/13
Model- 9/23/13
Testing procedures- 9/27/13
Developmental work- 10/25/13
FPU presentation outline- 10/30/13
FPU presentation- 10/31/13
Mentor contacts- 11/2/13
Presentation reflection- 2 days after personal presentation
Log sheets- Due weekly starting on 9/20/13

Working dates:
9/13/13-Finalize calendar on blog
9/14/13-Work on final design brief
9/15/13-Work on finished specifications and limitations
9/16/13-Reorganize alternate solutions
9/17/13- Preparation for informal presentation
9/18/13- Informal presentation and start rationale report
9/19/13- Work on rationale report
9/20/13- Construct model pump system
9/21/13- Construct model aeration system
9/22/13- Construct model heating system
9/23/13- Finishing details on model
9/24/13- Study NOAA heating tank systems
9/25/13- Work on math for pump system
9/26/13- Finalize testing procedures
9/27/13- Post testing procedures on blog
9/28/13- Search for pliable, clear tubing to be used in pump system
9/29/13- Work on alduino system for pump
9/30/13- Research power dampening effect on pumps
10/01/13- Practice programing alduino on pump
10/02/13- Finalize alduino programing research
10/03/13- Rule out separate air stone models
10/04/13- Research effects on air stones under sand
10/05/13- Discuss aeration of tank with mentors
10/06/13- Find proper location for tank cooler
10/07/13- Make sure tank cooler can keep tank at constant(or near constant) temperature
10/08/13- Find place to buy proper nutrients for horseshoe crabs
10/09/13- Make sure that the required amounts of nutrients can be purchased
10/10/13- Check that filtration system won’t reduce amount of nutrients
10/11/13- Find way to join filtration and pump systems
10/12/13- Make sure measurements of systems fit with tank design
10/13/13- Calculate math on drainage time
10/14/13- Check pump system so that more water is being produced than being drained
10/15/13- Talk to mentor to make sure of proper salinity
10/23/13- Finish developmental work
10/28/13- Write outline for presentation
10/29/13- Prepare for presentation
10/31/13- Make sure mentor contacts are recorded
11/1/13(Tentative date)-Write presentation reflection
Log sheets will be worked on each week.
 