Plan of Procedures
This plan of
procedure will detail exactly what steps I will go through in order to
construct each part of the water flow system. This system will consist of pvc
piping for the water transportation system and filtration system, environmental
controlling devices such as air stones, salinity meters, water chillers, and
thermometers, and materials to be used in the filtration system, which includes
a fine mesh net and a bacterial solution.
3D AutoCAD representation:
Parts needed:
|
Part name
|
Quantity
|
Use
|
|
|
2” PVC piping
|
10’
|
Pipes
|
|
|
PVC 90 degree elbow
|
6
|
PVC elbows
|
|
|
PVC couplings
|
10
|
Connect pipes
|
|
|
Air stones
|
4
|
Add DO to water
|
|
|
Coolworks Ice Probe with power supply
|
1
|
Cool water
|
|
|
Coolworks Proportional Temperature Controller
|
1
|
Control water
temperature
|
|
|
Aquarium Submersible Pump NP-80
|
1
|
Pump water through
system
|
|
|
Fine mesh net
|
1
|
Filter water
|
|
|
Mainstays kid’s 10
gallon rope tub
|
1
|
Reservoir tank
|
|
|
PVC Tee 2” connector
|
1
|
Connect pentagon piece to pipes
|
|
|
Tool name
|
Quantity
|
Use
|
|
Super glue
|
1
|
Seal holes
|
|
Drill
|
1
|
Drill in screws
|
|
Ruler
|
1
|
Measure
|
|
Heat gun
|
1
|
Heat PVC for bending
|
|
Sand
|
Not applicable
|
Fill PVC to avoid
pinching
|
|
Band saw
|
1
|
Cut PVC
|
|
Drill press
|
1
|
Drill holes in PVC
|
|
Compass
|
1
|
Measure angles
|
Procedure:
1.
Purchase
equipment for construction
2.
Cut
36.11” piece from 2” X 10’ PVC pipe(P1) using band saw(T6)
3.
Cut
36.11” piece in to 5 equal sized pieces of 7.22” using band saw(T6)
4.
Fill
each piece with sand(T5) and lay them upon floor
5.
Using
heat gun(T4), heat PVC until malleable. Then using compass(T8), make a 72 degree
angle in the center of each piece.
6.
Connect
pieces using PVC couplings(P3).
7.
Using
band saw(T6), cut 4” from the middle of one side of the pentagon and attach PVC
Tee connector(P10) to the couplings(P3).
8.
Attach
PVC 90 degree connector piece(P2) to PVC Tee connector(P10).
9.
Cut
a 22” piece from the 2” X10’ PVC pipe(P1) using the band saw(T6)
10. Connect 22” piece to the first 90
degree connector(P2) and then add another 90 degree connector(P2) to the other
end of the 22” piece.
11. Cut a 1” piece from the 2” X 10’ PVC
pipe(P1) and connect the 1” piece to the 90 degree connector piece(P2).
12. Using drill press(T7), drill 2” hole
in side of Mainstay’s 10 gallon kid’s rope tub(P9) and seal with super
glue(T1).
13. Using drill press(T7), drill 1” hole
in opposite side of Mainstay’s 10 gallon kid’s rope tub(P9) 1” from the bottom.
14. Insert Coolworks Iceprobe(P5) and
seal with super glue(T1) and attach Coolworks Iceprobe temperature
controller(P6) with cables.
The tank design that this Plan of Procedures was based off of is currently inaccurate, as Ms. Synek has re-designed the tank in order to maximize efficiency. This Plan of Procedures acts as an introduction to the methods that will be used to construct the tank.